Fruit & Wool Exchange London
SkySteel Structures Ltd were successful in the tendering of the erection package of this project for William Hare Ltd.
The total weight of the project was 3,400 T with 3,800 pieces to erect, plus 500 fin plates to prep, Engineer and weld in position.
With a total of just over 1 month of down time due to inclement weather, we were able to handover the complete project before the target completion date with no recorded incidents and while recording the highest daily erection piece count to date for William Hare Ltd. It was a testament to how hard the full team had worked.